Migrate Scenario
This scenario is intended for existing customers with an on-premises WALLIX PAM deployment who want to take advantage of all the benefits of WALLIX One PAM.
IMPORTANT
This scenario is designed for a single-phase migration, where all users and targets are transitioned to WALLIX One PAM in one go. For a more gradual or phased migration approach, please reach out to the WALLIX team for tailored assistance.
Scenario steps
This deployment consists of two main phases:
- Deployment phase that is similar to the previous scenario
- Migration phase managing data collection and transfer to WALLIX One PAM. In details:
Timeline
Depending on project teams availability, this scenario can be completed within 2 to 5 weeks.
Service interruption
Technically, no service interruption is required for this scenario. However, an interruption may be planned by the customer or the partner's project management. The on-prem solution can remain in production until the entire migration project is completed.
IMPORTANT
WALLIX strongly recommends disabling all secret rotation workflows (scheduled rotation, check-in rotation, manual rotation) in the on-prem deployment to prevent any desynchronization during the migration.